Overall ITR Progress

78.5%
ITR Validated: 1,247 / 1,586

Electrical ITR

82.3%
Validated: 456 / 554

Instrumentation ITR

75.8%
Validated: 423 / 558

Telecom ITR

85.2%
Validated: 368 / 432

Active Test Teams

24
Working on 47 tests

Critical Punch Items

8
Require immediate attention

System Completion Status

MCC-01 (Motor Control Center) 100% - SAT Completed
DCS (Distributed Control System) 67% - Loop Check in Progress
PA/GA (Public Address/General Alarm) 23% - FAT in Progress
Fire & Gas Detection System 0% - Not Started

Real-time ITR Activity

System Alerts

Inspection Sheets Status

Sheet Number Equipment Tag Phase Remaining Tests Punch Items Compliant Tests Total Tests
Click "Refresh Data" to load inspection sheets